Passing The Holy Milestone: How To Meet Deadlines


For too many projects, there comes a time when every action taken, every decision and sacrifice made, is spurred on by pressure to finish. Tempers seem to shrink along with the available days, talk about “high standards” gives way to “good enough,” and people realize that deadlines are aptly named. During the last-minute crunch, someone may well wonder, how did it come to this? Could it have been prevented? Every Web project has deadlines. But not every designer or developer deals with them the same way.

What Causes A Deadline To Break? Link

Because a deadline marks the end of a project, everyone involved in the project must understand the deadline’s role. Most projects follow a schedule or have an estimated date by which they must be completed. The concept is simple then: when the work takes longer than expected, deadlines get missed.

A deadline is the end point of a time estimate, making it a known quantity. But how long will the work actually take to get done?

Of course, projects can be more complicated in their details. Unexpected technical problems and unanticipated changes will affect the amount of work required. Sometimes other tasks take priority. Sometimes the time estimate wasn’t considered carefully enough.

Whatever the cause, too much work needs to be done in the available time. That’s the problem, but not the challenge.

Rate Deadlines By Severity Of Consequences Link

The hardest deadlines are tied to events that cannot be moved, such as a date promised to the public, an upcoming trade show or a date stipulated in a contract. Retailers know that their holiday sales must end at Christmas, and theater owners can expect movie-goers to be upset if a 1:00 pm showing doesn’t start until 2:00. Likewise, if a website is tied to a time-sensitive event, its relevance is lost once the event has passed. Hard deadlines have clear consequences when missed.

chart that shows how the trouble caused by missing a deadline increases severely after it passes
Deadlines exist for a reason. The severity of the trouble caused by missing them increases dramatically after they have passed.

Deadlines tied to less public events are no less real, but a project will soldier on if the deadline slips. Company-imposed target dates, for example, rely less on public demand than on the temperament of managers. Meetings routinely start 10 minutes late because “something came up.”

The softest deadlines lack teeth or are set at some vague point in the future. That’s not always bad: not every missed deadline will cause a life-or-death crisis. But the same methods of solving the crisis apply. There are many strategies for handling a last-minute crisis. Most involve planning, setting priorities and knowing one’s limits.

Strategies For Preventing Deadline Crises Link

The beginning of a project is a great time to prevent problems later on.

The first solution is both obvious and difficult: do not take on a project that cannot be completed in the given time. Declining paid work requires discipline and confidence, but if the deadline is impossible, then the project may not be worth the money. Money cannot replace time.

Because deadlines with consequences are taken more seriously, keep a written list of definitive reasons why certain tasks must be completed by a given date. Losing money, customers and other assets create real incentives to work.

Schedule deadlines as specific tasks, not the ends of phases. Rather than “Content will be completed by 4 April 2010,” state “Review the content over lunch on 4 April 2010.” This ties the deadline to an event at which results must be shown. Mini-deadlines tied to specific events are more powerful than general statements.

chart that shows how occasional reviews can help eliminate last-minute panic
Making up for minor time discrepancies during the course of a project is easier than facing a big shortfall when no time is left.

Plan For Unpleasant Surprises Link

Incentive may not be the problem, though. Unexpected problems cause many people to break deadlines. Their unpredictability make these problems hard to plan for, and good intentions don’t help you see the future. The key is to recognize that, whatever their nature, problems will likely occur.

If everything seems accounted for in the project plan, then invent a problem. Keep it realistic: “reshoot staff photos” is more likely than “spontaneous server combustion,” but it doesn’t really matter. The point is to create extra time to allow for a deadline crisis. One rule of thumb is to add between half and all of a project’s expected duration. That is, increase the full time that has been budgeted by between 50 to 100% to allow for surprises.

A plan of time estimates for major tasks in a project could look something like this:

Task: Time allotted:
Content audit 15 hours
Develop content strategy 15 hours
Make WordPress theme changes 20 hours
Import data from old website 15 hours
Test on multiple browsers 5 hours
Total 70 hours

Being conservative, let’s take half of 70, which is 35. Now we invent a problem: say, having to retype all content from print-outs. Is 35 hours for that ridiculous? Perhaps. But obstacles are unexpected by nature, and they always steal time from an otherwise ideal budget.

chart that shows how the trouble caused by missing a deadline increases severely after it passes
Scheduling for unknowns is hard, but acknowledging that extra time is required will better align estimates with reality.

A line item needs to be added to the budget. It could be “Time to make changes” or “Allowance for unknowns.” The description isn’t as important as the fact that you have planned for surprises.

Is half of the original budget too much? It may drive cheaper clients away, but overestimating and finishing under the deadline is better than the alternative.

Mitigate A Deadline’s Threat By Adding Other Deadlines Link

Implement mini-deadlines within a project’s timeline. Mini-deadlines minimize last-minute problems by serving as checkpoints to gauge how far off track the schedule is, if at all, at certain phases.

  1. Start
    While the project is fresh in everyone’s mind, a schedule for the other phases should be set.
  2. First quarter
    Everyone involved should have a sense of whether they can work together. Work begins, and the pristine project on paper comes up against the sticky details of reality.
  3. Halfway point
    The bulk of the work happens here. If you doubled your estimate to account for surprises, you would actually be aiming to launch the project right now.
  4. Third quarter
    If everyone pushed to launch by the halfway point, then almost everything should be done by now. But it rarely is.
  5. Deadline
    Launch the project.
  6. Review
    Win or lose, everyone should ask what should have happened at each phase of the project? What should have been done to meet each mini-deadline along the way?

Notice that mini-deadlines are based on time, not task. Tasks have a way of expanding, of taking up more time than planned, which mini-deadlines should prevent. Think of a mini-deadline as a chance to review the project’s timeline. While this approach may not entirely stave off a deadline crisis, it gives you opportunities to catch and correct problems along the way.

Plan Sacrifices In Advance Link

Every project has absolute requirements, which are essentially the reasons the project exists at all or the problems it is designed to solve. But many also have supplemental requirements. If a project requires A, B and C, then by all means include D, E and F, but only with the understanding that they might have to wait.

For example, a newsletter is an important marketing tool for an e-commerce website, but less important than an easy-to-use cart and secure log-in page. Likewise, the top priority for a photo gallery should be to present photos. If the deadline is looming and the AJAX is buggy, then perhaps the blog should wait.

Marking certain features as secondary provides relief when things go wrong. These features don’t need to be cut, but their deadlines should be later than those of the core project.

Practice Link

Measure the rate at which you work by timing how long you take to perform various tasks. You want to figure out how much time you need to comfortably perform each task, not how fast you can get it done.

For example, the schedule might allow for 30 minutes to create a favicon. But in reality, it consumes 8 hours.

Wait a minute. Eight hours for a measly 16×16-pixel graphic? Isn’t that… excessive?

That’s not the point. You’re not learning the rate at which you work so that you can gasp in embarrassment at the result. Workflow efficiency can be improved later. The question is, how much time are you comfortable with right now? In this case, it’s 8 hours.

Deadlines aren’t the problem. Problems arise when the work outweighs the allotted time. Learning how long you take to accomplish certain tasks is the best way to set a realistic schedule.

Conclusion Link

Not every deadline drama can be prevented, but even the worst can be dealt with professionally. Prepare for surprises, break up large tasks into manageable segments and prioritize. It’s a matter of respect: deadlines mean business. Do you?

How do you prevent deadline emergencies? What’s the worst problem you’ve faced under time pressure? What’s your greatest solution? Share your story in the comments below.


↑ Back to top Tweet itShare on Facebook

Ben Gremillion is a Writer at ZURB. He started his career in newspaper and magazine design, saw a digital future, and learned HTML in short order. He writes tutorials and facilitates the ZURB University training courses.

  1. 1

    Awesome article!
    I think that the big real problem in deadlines its that we always underestimate our capacity of putting ourselves in troubles.

    My advice is: break the activities into small pieces and iterate each one.

  2. 2

    Rodrigo Acevedo

    July 28, 2010 5:20 am

    I love the article!

  3. 3

    Good info, thanks for this article.

    I really like the trouble-time graph. :D

  4. 4

    Some interesting concepts. Will definitely have to incorporate some of the mitigation strategies suggested. Thx!

  5. 5

    I absolutely agree on this one. That concept also applies to real life scenarios other than work.

    Thanks for the wonderful idea.

  6. 6

    Great article. I’m a big fan of prioritising features with the client – especially when they keep adding them!

  7. 7

    Rightly said, I stopped for a moment and reliased.

    Its good to read. But its hard to follow.

  8. 8

    Two critiques to an excellent strategy. One, padding estimates by 50-100% may make for difficult estimates for your clients to swallow. In a job environment, your PM’s will likely want to know that you’re padding estimates, and by how much, so they have a realistic idea of the range of time you’re talking about, not to hand you more work, but to manage the project more effectively!

  9. 9

    Excelent article. But is kind difficult to follow when you have many projects. I think the mini deadlines could help a lot, it’s more easy finish short periods than see the long time to finish.

  10. 10

    Nice Article…

    I have recently faced this problem in my project. I have estimated the time and last time changes & adhoc issues left me frustrated when i missed my deadline :)

    This article definitely helps me a lot in future to handle this things professionally.

    Thanks again for this informative article, Ben.

  11. 11

    Mohammed Alnasiri

    July 28, 2010 7:25 am

    Mr : Ben Gremillion

    Thank you for this great article, & I need to talk to you regarding it for purpose of translating it into another language for the sake of sharing content but I need to get your permission on that.


  12. 12

    SCRUM works really well if all team members work by it. Since we addapted it in our company meeting deadlines is not the main problem anymore.

  13. 13

    Great Article… I love the idea of implementing mini-deadlines at the start of the project. I continuously deal with quickly approaching deadlines and am always looking for ways to streamline my workflow. By using mini-deadlines it allows you to have more control of the timeline.

  14. 14

    Many terrific points to present to the client with the creative brief. If you lay out the possible trouble spots and the consequences (more time = more money), they are more apt to understand that a four week project will become and eight week project if there are delays on their end. The charts would help the layperson to understand the process and time needed instead of three weeks to get you the content and one week to develop and implement the project (because that NEVER happens!).

    Great tips for every designer/developer!

  15. 15

    Christina Rosepapa

    July 28, 2010 9:15 am

    Good article. What about clients that let the deadlines pass?

  16. 16

    Oh the deadline.

    I’ve been a part of so many deadlines from corporate to freelance to charity work and this is a great starting point. I especially like tying checkpoints to events like “Review the content over lunch on 4 April 2010.” Great Advice! It’s easy to miss a “content due” deadline by a couple of days but really hard to miss lunch.

    You guys should also include related posts like links to managing client expectations when you do have deadline issues (i.e.

    It would be even MORE amazing if you added links to related posts/topics from the Smashing Network!

  17. 17

    I’m writing form Brazil. Can I translate this post. It’s a awesome article a I would like to spread it in portugues.
    Thanks in advance

    • 18

      eugenio, please feel free to translate at most 2 of our articles and publish them in your blog/publication. And if you do so please send us a link to the article once it’s published – we (probably) are building a list of translations for various articles…

      • 19

        oh if its possible, then I will translate some to Arabic =D
        and will consider sending you the link

  18. 20

    Nice article. I agree with previous comment that padding an estimate with 50%-100% will hardly win you any realistic bid. Especially in the crisis aftershock environment where more and more clients are demanding fixed price and fixed schedule quotes…

    One way to mitigate this is to use more formal approach to creating the estimate – like Function Point Analysis. Combining FPA and the history data (which this article point to) can give you much more confidence with fixed price quote…
    And by all means use the milestones to check the progress vs. estimates – that’s a life saving habit, if you can adopt it :)

  19. 21

    Brilliant article! – Thanks for sharing!

  20. 22

    Very academic and great article. Thanks

  21. 23

    Very useful article,
    Guys… Is it profitable for you to translate articles into Spanish?
    I’d like to read in Spanish. For now I use google translate.
    Thanks for sharing.

  22. 24

    Plan (and quote) for worst case scenario. I always put on an extra 33% of `fluff’ time in my quotes to cover myself for those wonderful surprises that happen in every job. You might need to be creative in explaining the extra hours to the client though up front.

  23. 25

    I don’t think that having a 50%-100% padding time is an effective way to deal with deadlines, You should focus towards more effective control, estimation and management of the project.

    Is good practice to have some time for unexpected tasks or problem, but something more realistic, adding 50 to 100% of extra time is almost to double the cost of the project “just in case”.

  24. 26

    Thanks for the post, I’m in need of something like this right about now (and still is breaking a certain deadline).

    I’ll try to implement something like this not only for work but for other stuff too.

  25. 27

    Great Article..Very Informative…!!

  26. 28

    Thanks much for such a useful material. Bookmarked.

  27. 29

    Creating mini deadlines sounds like a good idea.
    As the project is broken down in to smaller more manageable chunks.
    Also planning for problems is a good tip, as most web projects will cause you to have problems.
    I try to schedule at least an extra hour at the end of each project so I have time to rectify any issues.

  28. 30

    I work as the senior designer for a creative company in Thailand. I am in fact the only designer that treats with western clients that have a business here in Asia. And the amount of work that hangs on my shoulders is immense.
    I have tried by all means to set deadlines very similar to your ones by prioritizing the most important features. But since I am just a puppet behind the master puppeteer, I only get insensible deadlines that affect my workload. And to go further, I not only have to deal with web design, but also with 3D design, photography, Illustrations, package design and the list it goes on and on.

    My point is, being the corporate puppet, and only being one of yourself in charge of 8 projects that have in common the same deadline, the management time it just get’s blown apart.

  29. 31

    Very nice one

  30. 32

    A lot of times I take on projects that involve learning a new skill. I get excited about the project and think “this will be great!” but then after two hours of thrashing online Google for the answer, I start to realize I underestimated the time it would take to finish the project. I’m usually too overzealous at the onset and need to face it with realistic expectations first, before disappointing my team later. It’s just that I don’t know how to estimate the time it takes to do a new project…


↑ Back to top